County Building Permits

Platte County, WY - 2026 Building Permit Guide

How to apply for a building permit in unincorporated Platte County, Wyoming. Permit authority, application steps, fees, and inspection requirements.

Wyoming Updated March 2026

Permit Authority

Covers all construction in unincorporated areas of Platte County. Does not apply inside the incorporated limits of Wheatland, Guernsey, or Hartville. Platte County is a rural agricultural and ranching county in southeastern Wyoming, bisected by the North Platte River.

Department
Platte County Planning and Zoning Department
Address
Platte County Courthouse, 800 9th Street, Wheatland, WY 82201
Phone
(307) 322-3555

Online Permit Portal

Platform:Account required: No • Submission: In-person only

Additional resources:

Application Process

  1. Contact Platte County Planning and Zoning at (307) 322-3555 or visit the courthouse at 800 9th Street, Wheatland to determine whether a permit is required for your project and which application form applies.
  2. Obtain the applicable permit application form from the Planning and Zoning office.
  3. Prepare required documents: completed application, site/plot plan showing property boundaries, setbacks, and proposed structure location; construction drawings (floor plan, elevations, structural details); and any additional specialty plans as required.
  4. Submit completed application with all supporting documents to Planning and Zoning staff in person.
  5. Pay applicable permit fees at time of submission.
  6. Application enters staff review. Turnaround time varies; contact the office for current processing times.
  7. Respond to any staff comments or requests for additional information.
  8. Permit is issued once review is complete and fees are paid in full.
  9. Post permit on site in a visible location before work begins.
  10. Schedule required inspections through Planning and Zoning or contact staff for inspector referral.
  11. Receive final inspection sign-off. Certificate of occupancy (if applicable) is issued by county staff.

Typical processing time: Not publicly posted. Contact Platte County Planning and Zoning at (307) 322-3555 for current turnaround times. Rural county offices typically review small residential projects within 1-2 weeks; commercial and larger projects may take longer.

Source: Platte County Planning and Zoning Department

General Requirements

A building permit is required for any new construction, addition, structural alteration, repair, relocation, demolition, or change of occupancy within unincorporated Platte County, unless specifically exempt under the adopted code or local ordinance. Agricultural structures used exclusively for farming or ranching operations on qualifying agricultural properties may be exempt under Wyoming law -- confirm with Planning and Zoning.

Required Documents

  • Completed permit application
  • Site/plot plan drawn to scale showing property lines, structure footprint, setbacks from all property lines, driveway access, and utility locations
  • Construction drawings including floor plan, exterior elevations, and structural framing details
  • Foundation plan or specification
  • Energy compliance documentation where required under the adopted code
  • Drainage plan or grading plan for new construction on lots where drainage is a concern
  • Engineered plans (Wyoming-licensed P.E. stamp) for non-standard structural systems, retaining walls over 4 feet, or commercial projects
Permit validity
Not publicly posted for Platte County specifically. Wyoming standard under IRC Section R105.5 is 180 days without inspected work activity; confirm current county policy with Planning and Zoning. Extensions may be available upon written request.
Building code
Platte County is subject to Wyoming statewide building code requirements. Wyoming adopted the 2024 International Building Code (IBC), 2024 International Residential Code (IRC), and related 2024 International Codes effective June 28, 2024, with a 6-month window for local jurisdictions to adopt. Confirm with Platte County Planning and Zoning which edition and any local amendments are currently in effect. Platte County is a low-density rural county; code administration may be limited in scope compared to urban counties.
Owner-builder
Wyoming does not require a state general contractor license; homeowners may pull their own permits and serve as their own general contractor. Confirm owner-builder documentation requirements with Platte County Planning and Zoning.
Contractor requirements
Wyoming has no statewide general contractor license requirement. Electrical contractors must hold a state-issued license and obtain a Wyoming State Fire Marshal (WSFM) wiring permit for all electrical work. Plumbing and mechanical contractors should confirm local or state registration requirements. Platte County does not appear to maintain a separate local contractor licensing or registration program for unincorporated areas -- verify with Planning and Zoning.

Fees

Payment note
In-person payment at the courthouse; cash, check, or money order likely accepted. Credit/debit card acceptance not confirmed -- contact office before visit.

Work That Does NOT Require a Permit

  • Agricultural structures used exclusively for farm or ranch use not serving the public, subject to Wyoming law (W.S. 35-9-101 et seq.) exemptions for bona fide agricultural lands.

Important: Confirm specific exemption criteria and documentation requirements with Platte County Planning and Zoning.

Inspections

How to Schedule

  • ()
Inspection hours
Platte County Courthouse general hours: Monday through Friday, 8:00 a.m. to 5:00 p.m. Mountain Time; confirm Planning and Zoning office hours directly.
Time windows
Inspector availability in rural counties can be limited -- request scheduling well in advance of planned work stages.

Typical inspection sequence: Typical inspection sequence for residential construction: 1. Foundation/footing inspection (before pouring concrete), 2. Underground utilities/plumbing (before backfill), 3. Framing inspection (after rough framing is complete, before insulation or sheathing), 4. Rough mechanical, plumbing, and electrical (coordinate electrical with WSFM; rough-in before walls are closed), 5. Insulation inspection, 6. Wallboard/sheathing, 7. Final inspection (all work complete, ready for occupancy). Electrical inspections are handled separately by the Wyoming State Fire Marshal, not Platte County.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Platte County Planning and Zoning Department before applying.

Frequently Asked Questions

Platte County Building Permit FAQ

Do I need a building permit in unincorporated Platte County, WY?
A building permit is required for any new construction, addition, structural alteration, repair, relocation, demolition, or change of occupancy within unincorporated Platte County, unless specifically exempt under the adopted code or local ordinance. Agricultural structures used exclusively for farming or ranching operations on qualifying agricultural properties may be exempt under Wyoming law -- confirm with Planning and Zoning.
How do I apply for a building permit in unincorporated Platte County, WY?
1. Contact Platte County Planning and Zoning at (307) 322-3555 or visit the courthouse at 800 9th Street, Wheatland to determine whether a permit is required for your project and which application form applies. 2. Obtain the applicable permit application form from the Planning and Zoning office. 3. Prepare required documents: completed application, site/plot plan showing property boundaries, setbacks, and proposed structure location; construction drawings (floor plan, elevations, structural details); and any additional specialty plans as required. 4. Submit completed application with all supporting documents to Planning and Zoning staff in person. 5. Pay applicable permit fees at time of submission. 6. Application enters staff review. Turnaround time varies; contact the office for current processing times. 7. Respond to any staff comments or requests for additional information. 8. Permit is issued once review is complete and fees are paid in full. 9. Post permit on site in a visible location before work begins. 10. Schedule required inspections through Planning and Zoning or contact staff for inspector referral. 11. Receive final inspection sign-off. Certificate of occupancy (if applicable) is issued by county staff.
How long does it take to get a building permit in unincorporated Platte County, WY?
Typical processing time is Not publicly posted. Contact Platte County Planning and Zoning at (307) 322-3555 for current turnaround times. Rural county offices typically review small residential projects within 1-2 weeks; commercial and larger projects may take longer..
What work is exempt from building permits in unincorporated Platte County, WY?
The following work is generally exempt: Agricultural structures used exclusively for farm or ranch use not serving the public, subject to Wyoming law (W.S. 35-9-101 et seq.) exemptions for bona fide agricultural lands.. Note: Confirm specific exemption criteria and documentation requirements with Platte County Planning and Zoning.
How do I schedule a building inspection in unincorporated Platte County, WY?
Inspections can be scheduled via: .

Need help with your project?

Navigating permits in Unincorporated Platte County can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.
← Back to Platte County permit guides