Permit Authority

Montour County Zoning Office issues zoning permits for Anthony Township, Liberty Township, Mayberry Township, and Washingtonville Borough only. UCC building permit enforcement remains municipal or contracted municipal in each jurisdiction. There is no countywide general building-permit department.

Department
Montour County Zoning Office
Address
435 East Front Street, Danville, PA 17821
Phone
(570) 271-3021

Online Permit Portal

Platform:Account required: No • Submission: In-person only

Application Process

  1. Determine whether the parcel is in one of the four county-zoned municipalities: Anthony Township, Liberty Township, Mayberry Township, or Washingtonville Borough.
  2. Submit the zoning application with correct fees and supporting documents to the county zoning office.
  3. Obtain any required floodplain, sewage, driveway, planning, or conservation approvals that apply to the project.
  4. If a zoning hearing or conditional use is needed, submit the related hearing application and fees.
  5. After zoning approval, obtain any separate municipal or third-party UCC building permit required for the specific municipality.

Source: Montour County Zoning Office

General Requirements

The county zoning office issues zoning permits for Anthony Township, Liberty Township, Mayberry Township, and Washingtonville Borough. A zoning application, fees, and supporting documents are required. UCC building permit requirements are determined at the municipal level.

Required Documents

  • Zoning permit application
  • Correct fees
  • Supporting documents (sewage, driveway, floodplain, planning, conservation approvals as applicable)
  • Zoning hearing or conditional use application if required
Building code
Pennsylvania Uniform Construction Code (UCC); countywide UCC enforcement is not administered by the county — enforcement remains municipal or contracted.
Contractor requirements
No county contractor license requirement. Pennsylvania home improvement contractors performing work over $5,000 must register under the Pennsylvania Home Improvement Consumer Protection Act (HICPA).

Fees

Minimum permit fee
$50 application fee
Permit fee formula
Mixed flat and cost-based schedule. Commercial building zoning permits: $500 up to $50,000 construction cost, then plus $2 per $1,000 over $50,000. Non-commercial single-family detached: $300 up to $50,000, then plus $2 per $1,000 over $50,000. Accessory additions and detached structures: $50 plus $5 per $1,000 cost. Pools: $50 plus $5 per $1,000 cost. Demolition: $100 private, $200 business.
Payment note
Correct fees must accompany the application.

Fees change. Verify current amounts at the official fee schedule.

Work That Does NOT Require a Permit

Contact the Montour County Zoning Office to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

Inspection hours
Monday through Friday, 9:00 a.m. to 4:00 p.m.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Montour County Zoning Office before applying.

Frequently Asked Questions

Montour County Building Permit FAQ

Do I need a building permit in unincorporated Montour County, PA?
The county zoning office issues zoning permits for Anthony Township, Liberty Township, Mayberry Township, and Washingtonville Borough. A zoning application, fees, and supporting documents are required. UCC building permit requirements are determined at the municipal level.
How much does a building permit cost in unincorporated Montour County, PA?
The minimum permit fee is $50 application fee. Fees are calculated as: Mixed flat and cost-based schedule. Commercial building zoning permits: $500 up to $50,000 construction cost, then plus $2 per $1,000 over $50,000. Non-commercial single-family detached: $300 up to $50,000, then plus $2 per $1,000 over $50,000. Accessory additions and detached structures: $50 plus $5 per $1,000 cost. Pools: $50 plus $5 per $1,000 cost. Demolition: $100 private, $200 business..
How do I apply for a building permit in unincorporated Montour County, PA?
1. Determine whether the parcel is in one of the four county-zoned municipalities: Anthony Township, Liberty Township, Mayberry Township, or Washingtonville Borough. 2. Submit the zoning application with correct fees and supporting documents to the county zoning office. 3. Obtain any required floodplain, sewage, driveway, planning, or conservation approvals that apply to the project. 4. If a zoning hearing or conditional use is needed, submit the related hearing application and fees. 5. After zoning approval, obtain any separate municipal or third-party UCC building permit required for the specific municipality.

Need help with your project?

Navigating permits in Montour County can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.
← Back to Montour County permit guides