County Building Permits

Tillamook County, OR - 2026 Building Permit Guide

How to apply for a building permit in unincorporated Tillamook County, Oregon. Permit authority, application steps, fees, and inspection requirements.

Oregon Updated March 2026

Permit Authority

All properties in unincorporated areas of Tillamook County. Note: The county administers permits for several incorporated cities by intergovernmental agreement.

Department
Community Development Department
Address
1510 3rd Street, Suite B, Tillamook, Oregon 97141
Phone
(503) 842-1815

Online Permit Portal

Platform: Accela • Account required: Yes • Submission: In-person only

Additional resources:

Application Process

  1. Schedule an appointment with Tillamook County Community Development for permit submittal
  2. Submit complete application package (incomplete applications will not be accepted)
  3. County staff reviews for completeness and routes for required approvals
  4. Upon permit issuance, pick up permit within 5 business days or it will be mailed
  5. Schedule inspections as needed for foundation, framing, trades, and final approval
  6. Maintain continuous work; 180-day gaps between inspections will cause permit to expire

Source: Community Development Department

General Requirements

Building permits required for all construction in unincorporated Tillamook County

Required Documents

  • Completed permit application
  • Site plan
  • Construction plans
  • Official survey (required for any new construction or alterations that increase structural area toward any lot line)
Permit validity
Permits valid for 180 days from issuance. First approved inspection must occur within 180 days or permit expires. Each approved inspection extends permit another 180 days.
Building code
2014 Oregon Specialty Codes (structural, residential, plumbing, electrical, mechanical, energy efficiency)
Contractor requirements
Oregon Construction Contractors Board (CCB) license required for most construction work

Fees

Permit fee formula
Calculated using International Code Council Valuation Data Table (updated annually April 1). 3% technology fee applied to all applications/permits.
Reinspection fee
Charged for inspections beyond standard allowance
Payment note
Contact county for current fee structure. Excise taxes apply: $1.45/sq ft for residential; $0.72/sq ft for nonresidential.

Fees change. Verify current amounts at the official fee schedule (effective April 1, 2025).

Work That Does NOT Require a Permit

  • Manufactured dwelling placement permits available
  • Sheds and accessory structures: Generally exempt if under 200 sq ft and have no electrical, plumbing, or HVAC systems

Inspections

How to Schedule

Inspection hours
8:00 a.m. to 4:00 p.m. Monday-Friday

Typical inspection sequence: Inspections required per state building code: structural, trade, and Short Term Rental inspections available. Online scheduling available through BuildingPermits.Oregon.gov for some permit types.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Community Development Department before applying.

Frequently Asked Questions

Tillamook County Building Permit FAQ

Do I need a building permit in unincorporated Tillamook County, OR?
Building permits required for all construction in unincorporated Tillamook County
How much does a building permit cost in unincorporated Tillamook County, OR?
Fees are calculated as: Calculated using International Code Council Valuation Data Table (updated annually April 1). 3% technology fee applied to all applications/permits..
How do I apply for a building permit in unincorporated Tillamook County, OR?
1. Schedule an appointment with Tillamook County Community Development for permit submittal 2. Submit complete application package (incomplete applications will not be accepted) 3. County staff reviews for completeness and routes for required approvals 4. Upon permit issuance, pick up permit within 5 business days or it will be mailed 5. Schedule inspections as needed for foundation, framing, trades, and final approval 6. Maintain continuous work; 180-day gaps between inspections will cause permit to expire
What work is exempt from building permits in unincorporated Tillamook County, OR?
The following work is generally exempt: Manufactured dwelling placement permits available; Sheds and accessory structures: Generally exempt if under 200 sq ft and have no electrical, plumbing, or HVAC systems.
How do I schedule a building inspection in unincorporated Tillamook County, OR?
Inspections can be scheduled via: (503) 842-1815 (Inspection Hotline), BuildingPermits.Oregon.gov.

Need help with your project?

Navigating permits in Tillamook County (Unincorporated) can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.