Permit Authority

City of Tallmadge, including the portion in Portage County

Department
Planning and Zoning Department; building permits are issued by Summit County Department of Building Standards
Address
46 North Avenue, Tallmadge, OH 44278
Phone
330-633-0090

Application Process

Typical processing time: Zoning application may take up to 14 business days

Source: Planning and Zoning Department; building permits are issued by Summit County Department of Building Standards

General Requirements

Zoning certificate required before new construction, additions, fences, pools, decks, and other projects; building permits are then issued by Summit County

Required Documents

  • Zoning Certificate Application, detailed site plan, one set of building plans with elevated view
Building code
Summit County Department of Building Standards handles building and occupancy permits under Ohio code
Contractor requirements
Contractor registration is required for right-of-way or utility easement work; building permit contractor rules are handled through the county system

Work That Does NOT Require a Permit

Contact the Planning and Zoning Department; building permits are issued by Summit County Department of Building Standards to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • Inspections must be scheduled through the Water Department for water and sewer related work; building inspections are ha (contact)
Inspection hours
City office Monday-Friday 7:30 a.m. to 4 p.m.

Typical inspection sequence: Zoning certificate, building permit, fire inspections, building permit issuance and inspections through Summit County

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Planning and Zoning Department; building permits are issued by Summit County Department of Building Standards before applying.

Frequently Asked Questions

Tallmadge Building Permit FAQ

Do I need a building permit in Tallmadge, OH?
Zoning certificate required before new construction, additions, fences, pools, decks, and other projects; building permits are then issued by Summit County
How long does it take to get a building permit in Tallmadge, OH?
Typical processing time is Zoning application may take up to 14 business days.
How do I schedule a building inspection in Tallmadge, OH?
Inspections can be scheduled via: Inspections must be scheduled through the Water Department for water and sewer related work; building inspections are ha.

Need help with your project?

Navigating permits in Tallmadge can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in Portage County

View all Portage County jurisdictions →