City Building Permits

Village of Campbell, NE - 2026 Building Permit Guide

How to apply for a building permit in Village of Campbell, Nebraska. Permit authority, application steps, fees, and inspection requirements.

Nebraska Franklin County Updated March 2026

Permit Authority

All properties within the incorporated Village of Campbell.

Department
Village of Campbell — Village Office
Address
721 Broad Street, P.O. Box 215, Campbell, NE 68932
Phone
(402) 756-8121

Online Permit Portal

Platform: Paper-based • Account required: No • Submission: In-person only

Application Process

  1. Contact the Village of Campbell Village Office at (402) 756-8121 to obtain a building permit application and confirm current requirements and fee schedule.
  2. Review the applicable sections of the Campbell Code of Ordinances — Title XV (Land Usage) and the Building Permits and Regulations chapter.
  3. Complete and submit the application with applicable fee and required documentation to the Village Clerk.
  4. Allow for review and approval by village officials before commencing work.
  5. Obtain Nebraska State Electrical Division (NSED) electrical permit for any electrical work.
  6. For commercial or public-assembly projects, submit plans to the Nebraska State Fire Marshal (NSFM) for fire/life safety plan review.
  7. If construction disturbs one or more acres, obtain an NDEE Construction Stormwater General Permit (Notice of Intent) before breaking ground.

Typical processing time: Contact the Village Office for current timelines.

Source: Village of Campbell — Village Office

General Requirements

Campbell's Code of Ordinances includes building permit requirements under its Building Permits and Regulations chapter. Review this chapter for the specific permit triggers, required application contents, and fee structure.

Required Documents

  • Completed building permit application
  • Site plan (as required by village ordinances)
  • Project description
  • Property address or legal description
Building code
Campbell Code of Ordinances, Title XV (Land Usage) and Building Permits and Regulations chapter. Nebraska state building code (2018 IBC/IRC) applies as default framework. Nebraska Energy Code: 2018 International Energy Conservation Code (IECC) mandatory statewide.
Contractor requirements
Contractors and subcontractors with Nebraska employees must register annually with the Nebraska Department of Labor (NDOL) — registration is distinct from a state general contractor license, which does not exist in Nebraska. Cost: $25/year; workers' compensation certificate required. Website: https://dol.nebraska.gov/conreg

Work That Does NOT Require a Permit

Contact the Village of Campbell — Village Office to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • (402) 756-8121 (phone)

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Village of Campbell — Village Office before applying.

Frequently Asked Questions

Village of Campbell Building Permit FAQ

Do I need a building permit in Village of Campbell, NE?
Campbell's Code of Ordinances includes building permit requirements under its Building Permits and Regulations chapter. Review this chapter for the specific permit triggers, required application contents, and fee structure.
How do I apply for a building permit in Village of Campbell, NE?
1. Contact the Village of Campbell Village Office at (402) 756-8121 to obtain a building permit application and confirm current requirements and fee schedule. 2. Review the applicable sections of the Campbell Code of Ordinances — Title XV (Land Usage) and the Building Permits and Regulations chapter. 3. Complete and submit the application with applicable fee and required documentation to the Village Clerk. 4. Allow for review and approval by village officials before commencing work. 5. Obtain Nebraska State Electrical Division (NSED) electrical permit for any electrical work. 6. For commercial or public-assembly projects, submit plans to the Nebraska State Fire Marshal (NSFM) for fire/life safety plan review. 7. If construction disturbs one or more acres, obtain an NDEE Construction Stormwater General Permit (Notice of Intent) before breaking ground.
How long does it take to get a building permit in Village of Campbell, NE?
Typical processing time is Contact the Village Office for current timelines..
How do I schedule a building inspection in Village of Campbell, NE?
Inspections can be scheduled via: (402) 756-8121.

Need help with your project?

Navigating permits in Village of Campbell can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.