How to apply for a building permit in unincorporated Hill County, Montana. Permit authority, application steps, fees, and inspection requirements.

Montana Updated March 2026

Permit Authority

No local building permit authority. State jurisdiction for building codes.

Department
Building & Commercial Measurements Bureau, Montana Department of Labor & Industry
Address
301 S. Park Avenue, 4th Floor, Helena, MT
Phone
406-841-2056

Online Permit Portal

Platform: State Accela system • Account required: No • Submission: In-person only

Application Process

  1. Verify zoning with Hill County Planning: 406-265-5481
  2. Submit state building permit application through EBIZ.MT.GOV if required
  3. State reviews plans (2-3 weeks)
  4. Address comments
  5. Pay fees
  6. Permit issued

Typical processing time: 2-3 weeks

Source: Building & Commercial Measurements Bureau, Montana Department of Labor & Industry

General Requirements

Per state thresholds for new structures, alterations

Building code
Montana 2021 IBC with amendments

Fees

Permit fee formula
1-2% of project valuation

Work That Does NOT Require a Permit

Contact the Building & Commercial Measurements Bureau, Montana Department of Labor & Industry to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • ()
Scheduling deadline
24 hours before inspection

Typical inspection sequence: Response window: 72 hours

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Building & Commercial Measurements Bureau, Montana Department of Labor & Industry before applying.

Frequently Asked Questions

Hill County Building Permit FAQ

Do I need a building permit in unincorporated Hill County, MT?
Per state thresholds for new structures, alterations
How much does a building permit cost in unincorporated Hill County, MT?
Fees are calculated as: 1-2% of project valuation.
How do I apply for a building permit in unincorporated Hill County, MT?
1. Verify zoning with Hill County Planning: 406-265-5481 2. Submit state building permit application through EBIZ.MT.GOV if required 3. State reviews plans (2-3 weeks) 4. Address comments 5. Pay fees 6. Permit issued
How long does it take to get a building permit in unincorporated Hill County, MT?
Typical processing time is 2-3 weeks.
What work is exempt from building permits in unincorporated Hill County, MT?
The following work is generally exempt: Farm/ranch buildings; Residential under 5 units; Mining buildings; Private owner-use storage/garages.
How do I schedule a building inspection in unincorporated Hill County, MT?
Inspections can be scheduled via: . 24 hours before inspection.

Need help with your project?

Navigating permits in Town of Rudyard can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.
← Back to Hill County permit guides