Permit Authority

County permit path for unincorporated Ste. Genevieve County. County site states building permits are required countywide under a county ordinance adopted January 1, 1986. County page does not show a separate building department; public permit intake is through the Assessor's Office

Department
Assessor's Office / county permit intake
Address
55 South Third St., Room 4, Ste. Genevieve, MO 63670
Phone
573-883-2333 ext. 4

Online Permit Portal

Platform: None found • Account required: No • Submission: In-person only

Additional resources:

Application Process

  1. Confirm the property is in unincorporated Ste. Genevieve County and not inside a city limit
  2. Contact or visit the Assessor's Office for permit intake
  3. Confirm flood zone status before starting work
  4. Submit project details and any required drawings or supporting materials if requested by staff
  5. Receive the permit before starting construction
  6. Arrange inspections if the county requests them for the project

Typical processing time: Not publicly posted

Source: Assessor's Office / county permit intake

General Requirements

County page states building permits are required under county ordinance. Public page does not publish a detailed trigger list

Required Documents

  • When a permit is required: County page states building permits are required under county ordinance. Public page does not publish a detailed trigger list
  • Required documents: Not publicly listed
  • Permit validity/expiration: Not publicly listed
  • Owner-builder rules if available: Not publicly listed
  • Contractor license requirements: Not publicly listed
  • Building code adopted: County page references a county ordinance adopted January 1, 1986. Specific code edition not publicly listed
Permit validity
Not publicly listed
Building code
County page references a county ordinance adopted January 1, 1986. Specific code edition not publicly listed
Owner-builder
Not publicly listed
Contractor requirements
Not publicly listed

Fees

Minimum permit fee
No fee for a permit, per county Assessor page
Plan check fee
Not publicly listed
Permit fee formula
Flat no-fee permit, per public page
Reinspection fee
Not publicly listed
Payment note
Permit is described as easily issued by stopping by or calling the Assessor's Office; no payment appears to be required for the building permit itself

Fees change. Verify current amounts at the official fee schedule.

Work That Does NOT Require a Permit

Contact the Assessor's Office / county permit intake to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • Not publicly listed ()
Inspection hours
Assessor Office hours are Monday through Friday, 8:00 a.m. to 4:30 p.m

Typical inspection sequence: Not publicly listed

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Assessor's Office / county permit intake before applying.

Frequently Asked Questions

Ste Genevieve County Building Permit FAQ

Do I need a building permit in unincorporated Ste Genevieve County, MO?
County page states building permits are required under county ordinance. Public page does not publish a detailed trigger list
How much does a building permit cost in unincorporated Ste Genevieve County, MO?
The minimum permit fee is No fee for a permit, per county Assessor page. Fees are calculated as: Flat no-fee permit, per public page. Plan check fee: Not publicly listed.
How do I apply for a building permit in unincorporated Ste Genevieve County, MO?
1. Confirm the property is in unincorporated Ste. Genevieve County and not inside a city limit 2. Contact or visit the Assessor's Office for permit intake 3. Confirm flood zone status before starting work 4. Submit project details and any required drawings or supporting materials if requested by staff 5. Receive the permit before starting construction 6. Arrange inspections if the county requests them for the project
How long does it take to get a building permit in unincorporated Ste Genevieve County, MO?
Typical processing time is Not publicly posted.
What work is exempt from building permits in unincorporated Ste Genevieve County, MO?
The following work is generally exempt: No public exempt-work list was found on the county site.
How do I schedule a building inspection in unincorporated Ste Genevieve County, MO?
Inspections can be scheduled via: Not publicly listed.

Need help with your project?

Navigating permits in Ste. Genevieve County Unincorporated Area can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.
← Back to Ste Genevieve County permit guides