City Building Permits

Cameron, MO - 2026 Building Permit Guide

How to apply for a building permit in Cameron, Missouri. Permit authority, application steps, fees, and inspection requirements.

Missouri Clinton County Updated March 2026

Permit Authority

The department enforces the 2015 ICC Building Codes, the 2015 IRC (with minor revisions since May 2017), and the 2017 NEC for all new construction and improvements within city limits. citeturn7view0turn10view0

Department
Building Permits & Inspections, City of Cameron
Address
205 N. Main St., Cameron, MO 64429 (mailing address P.O. Box 20, Cameron, MO 64429-0020)
Phone
(816) 632-2177

Online Permit Portal

Application Process

  1. Submit two sets of drawings (foundation plan, floor plans, elevations, wall sections, emergency egress, wall bracing, and engineer/architect stamp) plus a detailed site plan before the inspector reviews the project. citeturn10view0
  2. Plan review should not take more than 30 working days, and construction must start within 180 days of issuance. citeturn10view0
  3. Pay permit fees based on finished square footage or estimated cost along with any stormwater, water tap, or sewer impact fees before the permit is issued. citeturn9view0turn10view0
  4. Acquire occupational licenses for everyone working on the project, and ensure electrical/mechanical/plumbing contractors show their Master licenses even if the general contractor has a blanket license. citeturn10view0
  5. Schedule inspections by calling (816) 632-2177 or emailing pbeckwith@cameronmo.com with 24 hours’ notice (4 hours for concrete/sewer); silt fences must stay in place and access must be maintained. citeturn10view0
  6. Request the occupancy inspection once all rough-ins, driveways, and site work comply; the inspector may issue a temporary occupancy while landscaping wraps up. citeturn10view0

Typical processing time: Plan review is targeted at 30 working days; no other timeframe is public. citeturn10view0

General Requirements

Cameron requires permits for all new buildings, additions, remodels, accessory structures, and demolition. citeturn7view0

Required Documents

  • When a permit is required: Cameron requires permits for all new buildings, additions, remodels, accessory structures, and demolition. citeturn7view0
  • Required documents: Submit two sets of stamped plans, a surveyor’s site plan showing setbacks/flood data, and details covering bracing, plumbing, electrical, and mechanical systems. citeturn10view0
  • Permit validity/expiration: Permits expire if construction does not begin within 180 days. citeturn10view0
  • Owner-builder rules if available: Occupational licenses are required for every worker, and registered trades must present proof of Master licensure. citeturn10view0
  • Contractor license requirements: Electrical, mechanical, and plumbing contractors must hold a Master license from a nationally accredited testing company. citeturn10view0
  • Building code adopted: The city enforces the 2015 International Building Codes (including the 2015 IRC with minor revisions) and the 2017 NEC. citeturn7view0turn10view0
Permit validity
Permits expire if construction does not begin within 180 days. citeturn10view0
Building code
The city enforces the 2015 International Building Codes (including the 2015 IRC with minor revisions) and the 2017 NEC. citeturn7view0turn10view0
Owner-builder
Occupational licenses are required for every worker, and registered trades must present proof of Master licensure. citeturn10view0
Contractor requirements
Electrical, mechanical, and plumbing contractors must hold a Master license from a nationally accredited testing company. citeturn10view0

Fees

Minimum permit fee
$40 for non-electrical remodeling and $60 for electrical minimums. citeturn9view0
Plan check fee
Stormwater plan review is $200 for single-family and $450 plus $50 per acre for larger sites; no separate building plan check fees are listed. citeturn9view0
Permit fee formula
New construction is $0.67 per square foot, remodels are $0.33 per square foot, and miscellaneous work uses estimated cost brackets (0.01 × estimated cost for projects ≥ $6,001); utility tap, stormwater review, and street-cut fees are also listed. citeturn9view0
Reinspection fee
A $50 late fee applies if construction begins before the permit is purchased, and demolition, reinspection, and extension fees are enumerated in the schedule. citeturn9view0
Payment note
The building page links to the city’s Online Bill Pay portal for fee settlement. citeturn7view0

Fees change. Verify current amounts at the official fee schedule.

Work That Does NOT Require a Permit

Contact the Building Permits & Inspections, City of Cameron to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • Call (816) 632-2177 or email pbeckwith@cameronmo.com for inspections with 24 hours’ notice (4 hours for concrete/sewer work). citeturn10view0 ()
Inspection hours
The Building Department is open Monday–Friday, 8:00 a.m.–5:00 p.m. citeturn7view0

Typical inspection sequence: The Building Guidelines list footing, wall, sewer, ground rough, erosion, wall bracing, rough-in, driveway/sidewalk, and occupancy inspections. citeturn10view0

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Building Permits & Inspections, City of Cameron before applying.

Frequently Asked Questions

Cameron Building Permit FAQ

Do I need a building permit in Cameron, MO?
Cameron requires permits for all new buildings, additions, remodels, accessory structures, and demolition. citeturn7view0
How much does a building permit cost in Cameron, MO?
The minimum permit fee is $40 for non-electrical remodeling and $60 for electrical minimums. citeturn9view0. Fees are calculated as: New construction is $0.67 per square foot, remodels are $0.33 per square foot, and miscellaneous work uses estimated cost brackets (0.01 × estimated cost for projects ≥ $6,001); utility tap, stormwater review, and street-cut fees are also listed. citeturn9view0. Plan check fee: Stormwater plan review is $200 for single-family and $450 plus $50 per acre for larger sites; no separate building plan check fees are listed. citeturn9view0.
How do I apply for a building permit in Cameron, MO?
1. Submit two sets of drawings (foundation plan, floor plans, elevations, wall sections, emergency egress, wall bracing, and engineer/architect stamp) plus a detailed site plan before the inspector reviews the project. citeturn10view0 2. Plan review should not take more than 30 working days, and construction must start within 180 days of issuance. citeturn10view0 3. Pay permit fees based on finished square footage or estimated cost along with any stormwater, water tap, or sewer impact fees before the permit is issued. citeturn9view0turn10view0 4. Acquire occupational licenses for everyone working on the project, and ensure electrical/mechanical/plumbing contractors show their Master licenses even if the general contractor has a blanket license. citeturn10view0 5. Schedule inspections by calling (816) 632-2177 or emailing pbeckwith@cameronmo.com with 24 hours’ notice (4 hours for concrete/sewer); silt fences must stay in place and access must be maintained. citeturn10view0 6. Request the occupancy inspection once all rough-ins, driveways, and site work comply; the inspector may issue a temporary occupancy while landscaping wraps up. citeturn10view0
How long does it take to get a building permit in Cameron, MO?
Typical processing time is Plan review is targeted at 30 working days; no other timeframe is public. citeturn10view0.
What work is exempt from building permits in Cameron, MO?
The following work is generally exempt: The public materials do not list exempt work; verify with the department. (thin public information).
How do I schedule a building inspection in Cameron, MO?
Inspections can be scheduled via: Call (816) 632-2177 or email pbeckwith@cameronmo.com for inspections with 24 hours’ notice (4 hours for concrete/sewer work). citeturn10view0.

Need help with your project?

Navigating permits in Cameron can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.