Permit Authority
Issues permits within the City of Centerville
- Department
- City of Centerville Building Inspections Department
- Address
- 300 E. Church Street, Centerville, GA 31028
- Phone
- Building Inspector John Burt: (478) 953-7871 ext. 242; City Clerk: (478) 953-4734
- jburt@centervillega.org
Application Process
- Contact the Building Inspections Department if the permit trigger is unclear
- Download the construction permit application or roofing permit application from the city site
- Submit the application and plans to the City Clerk office / Building Inspector at 300 E. Church Street
- Obtain review and approval from the Centerville Building Inspector and Utilities Superintendent before permit issuance
- Pay the required permit fees
- Schedule inspections through City Hall / Building Inspections during construction
Typical processing time: Site plan review can take about two weeks for basic review and up to 45 days when stormwater review is required
General Requirements
New residential and commercial construction, additions and alterations, miscellaneous changes and repairs or total replacement of electrical, plumbing, and HVAC systems, installation or relocation of mobile homes in approved parks, and swimming pools
Required Documents
- Permit application
- Building plans
- Contractor information
- Utilities review materials needed for the Utilities Superintendent
- For sign permits: colored rendering, dimensions, and site plan for freestanding signs
- Building code
- Building Inspection Department enforces the city's construction codes. No separate current local code-adoption ordinance was located; Georgia state minimum construction codes apply at minimum
- Owner-builder
- Building codes apply whether work is completed by a hired contractor or private homeowner
- Contractor requirements
- Application forms request state license information for general, plumbing, electrical, and HVAC contractors; Georgia state licensing rules apply
Fees
- Minimum permit fee
- $10.00 administrative fee
- Permit fee formula
- Mixed. Sign permit fees are based on a percentage of construction cost; multiple permit-specific charges by type
- Payment note
- Electronic payment processing fee: $1.80 per payment (effective August 7, 2023; non-refundable)
Fees change. Verify current amounts at the official fee schedule (effective 2020).
Work That Does NOT Require a Permit
Contact the City of Centerville Building Inspections Department to confirm whether your project requires a permit before starting work.
Inspections
How to Schedule
- ()
- ()
- Inspection hours
- Monday through Friday, 8:00 a.m. to 5:00 p.m.
Additional Resources
- Building code: Building Inspection Department enforces the city's construction codes. No separate current local code-adoption ordinance was located; Georgia state minimum construction codes apply at minimum
- Zoning information: View zoning info
- License lookup guide: Georgia Contractor License Requirements
- Contract template: Georgia Homeowner-Contractor Agreement
- Georgia hub: Georgia Contractor License & Permit Hub
Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the City of Centerville Building Inspections Department before applying.
Frequently Asked Questions
Centerville Building Permit FAQ
- Do I need a building permit in Centerville, GA?
- New residential and commercial construction, additions and alterations, miscellaneous changes and repairs or total replacement of electrical, plumbing, and HVAC systems, installation or relocation of mobile homes in approved parks, and swimming pools
- How much does a building permit cost in Centerville, GA?
- The minimum permit fee is $10.00 administrative fee. Fees are calculated as: Mixed. Sign permit fees are based on a percentage of construction cost; multiple permit-specific charges by type.
- How do I apply for a building permit in Centerville, GA?
- 1. Contact the Building Inspections Department if the permit trigger is unclear 2. Download the construction permit application or roofing permit application from the city site 3. Submit the application and plans to the City Clerk office / Building Inspector at 300 E. Church Street 4. Obtain review and approval from the Centerville Building Inspector and Utilities Superintendent before permit issuance 5. Pay the required permit fees 6. Schedule inspections through City Hall / Building Inspections during construction
- How long does it take to get a building permit in Centerville, GA?
- Typical processing time is Site plan review can take about two weeks for basic review and up to 45 days when stormwater review is required.
- How do I schedule a building inspection in Centerville, GA?
- Inspections can be scheduled via: , .
Need help with your project?
Navigating permits in Centerville can be complicated.
Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.
Learn how Jaspector worksOther cities in Houston County
View all Houston County jurisdictions →