County Building Permits
Glynn County, GA - 2026 Building Permit Guide
How to apply for a building permit in unincorporated Glynn County, Georgia. Permit authority, application steps, fees, and inspection requirements.
Permit Authority
Applies in unincorporated Glynn County outside the City of Brunswick
- Department
- Building Permitting and Inspections
- Address
- 1725 Reynolds Street, Suite 200, Brunswick, GA 31520
- Phone
- 912-554-7456
Online Permit Portal
Platform: OpenGov Citizen Services • Account required: Yes • Submission: Online only
Additional resources:
Application Process
- Apply through Glynn County's Citizen Services / OpenGov portal for building, planning, or engineering services applications
- Upload the required attachments as part of the application package
- County reviewers check the package for compliance with state and county regulations and will request resubmittal if items are noncompliant
- Once all reviewers determine the package is compliant, the application is approved; some related applications require public hearings before approval
- Fees and approval letters are handled through OpenGov; after permit issuance, inspections are scheduled by phone with the Building Department and a certificate of occupancy is issued after all inspections and required paperwork/forms are complete
General Requirements
New Construction and Additions, Structural Changes, Change in Building Use, Outdoor Structures and Site Work, Demolition and Removal, Specialized Installations, and Trade Work
Required Documents
- Application package with required attachments through OpenGov
- Elevation certificates for floodplain projects
- For manufactured/mobile homes: septic tank permit, driveway/culvert permit, tax decal, home make/year/value/size information
- Building code
- International Building Code 2024, International Residential Code 2024, International Fire Code 2024, International Plumbing Code 2024, International Mechanical Code 2024, International Fuel Gas Code 2024, International Energy Conservation Code 2015, International Swimming Pool and Spa Code 2024, National Electrical Code 2023, as mandated and amended by Georgia; 2026 Georgia amendments effective January 1, 2026
- Owner-builder
- Owner-performed work allowed; confirm directly with the department regarding home owner affidavit requirements
- Contractor requirements
- For manufactured/mobile home setup, the setup contractor must be licensed by both the State of Georgia and Glynn County; Georgia state licensing rules apply to residential contracting above the state threshold
Fees
- Payment note
- Planning and zoning application fees are paid only through OpenGov and approval letters are issued only within OpenGov; the county does not email invoices or request payment by email
Work That Does NOT Require a Permit
Contact the Building Permitting and Inspections to confirm whether your project requires a permit before starting work.
Inspections
How to Schedule
- ()
- Inspection hours
- Monday through Friday, 8:00 AM to 4:00 PM (phones open until 4:30 PM)
- Time windows
Typical inspection sequence: Common stages: footing before concrete, slab before pour, rough-in before drywall, permanent power between rough-in and final, and final after building, plumbing, electrical, HVAC, driveway/culvert, house number, landscaping, and soil erosion measures are complete; certificate of occupancy issued after all inspections and required paperwork/forms are complete
Additional Resources
- Building code: International Building Code 2024, International Residential Code 2024, International Fire Code 2024, International Plumbing Code 2024, International Mechanical Code 2024, International Fuel Gas Code 2024, International Energy Conservation Code 2015, International Swimming Pool and Spa Code 2024, National Electrical Code 2023, as mandated and amended by Georgia; 2026 Georgia amendments effective January 1, 2026
- Verify contractor license: Georgia Secretary of State
- Zoning information: View zoning info
- License lookup guide: Georgia Contractor License Requirements
- Contract template: Georgia Homeowner-Contractor Agreement
- Georgia hub: Georgia Contractor License & Permit Hub
Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Building Permitting and Inspections before applying.
Frequently Asked Questions
Glynn County Building Permit FAQ
- Do I need a building permit in unincorporated Glynn County, GA?
- New Construction and Additions, Structural Changes, Change in Building Use, Outdoor Structures and Site Work, Demolition and Removal, Specialized Installations, and Trade Work
- How do I apply for a building permit in unincorporated Glynn County, GA?
- 1. Apply through Glynn County's Citizen Services / OpenGov portal for building, planning, or engineering services applications 2. Upload the required attachments as part of the application package 3. County reviewers check the package for compliance with state and county regulations and will request resubmittal if items are noncompliant 4. Once all reviewers determine the package is compliant, the application is approved; some related applications require public hearings before approval 5. Fees and approval letters are handled through OpenGov; after permit issuance, inspections are scheduled by phone with the Building Department and a certificate of occupancy is issued after all inspections and required paperwork/forms are complete
- How do I schedule a building inspection in unincorporated Glynn County, GA?
- Inspections can be scheduled via: .
Need help with your project?
Navigating permits in Glynn County (Unincorporated) can be complicated.
Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.
Learn how Jaspector works